. Identify Stakeholders involved
. Identify team members
. Identify current forms and procedures
. Identify gaps and inadequacies in current procedures
. Identify redundancies in current procedures
. Identify obsolete and unnecessary forms & procedures
. Review existing methodologies used by the IT industry
. Publish recommended changes to procedures
. Obtain sign offs
1.1 Project Name: Jedi – Just Do It!
1.2 Project Description:
. Speed up and streamline production processes
. Eliminate wasteful and costly redundancies
. Combine forms and eliminate steps from approval procedures
1.3 Sponsor: Frank Spoto, Manager Student Information Systems (773) 553-1234
1.4 Project Manager: John Kraus, key team members Bob LoSasso, Lisa Washington
1.5 Deliverables:
. CPS Current Procedures Document
. Recommended Changes Document
. Approved Changes Document with Implementation Schedules
1.6 Reference Materials:
. Existing forms & written guidelines
. Samples of Industry Methodologies
1.7 Terms and Acronyms
. SDLC – System Development Life Cycle
2.1 Organizational Chart\\\

2.2 Project Responsibilities:
. John:
. Identify existing forms
. Eliminate redundant & unnecessary forms
. Improve needed forms
. Prepare forms for team review
. Bob:
. Identify existing written procedures
. Identify current sign-off procedures
. Prepare new procedures for team review
. Lisa
. Review other industry methodologies
. Prepare sample methodology for team review
2.3 Other Organizational or Process Related Information:
. Implementation steps diagram
3.1 Management Objectives:
. Decrease time it takes to implement system changes with a goal of no post implementation problems
. Priority is current system maintenance; constraint is little impact on existing projects
3.2 Project Controls
. Team reviews of individual project responsibilities
. Team walk-thru of proposed forms and procedures with sample project
. Project Management review of proposed forms and procedures
. Upper Management sign off of new forms and procedures
3.3 Risk Management
. Interview key staff in all departments; identify what does not happen when a form/procedure is eliminated
. Form or procedure can be reinstated if a loss or detriment to production
3.4 Project Staffing
. Existing three member team
. Review and feedback from Project Managers
. Sign-off by Upper Management
. Printer for new forms and written documentation
3.5 Technical Processes
. Design a form for documenting existing procedures and for approving changes
4.1 Major Work Packages
. Identify current forms & procedures
. Review existing industry SDLC methodologies
. Propose new forms & procedures
. Get management signoff
. Document and publish new forms, procedures
4.2 Key Deliverables
. Reduce time for expenditure approvals with no loss of paper trail
. Reduce time for vendor payments
. Revised forms manual
. Revised employee procedures manual
4.3 Other Work Related Information
. We assume people are willing to adopt new procedures if it makes their work easier
. We will use MS Project to manage the project
5.1 Summary Schedule
. Project runs November 2001 thru October 2002
5.2 Detail Schedule
. Identify departments internal and external to IT – November
. Interviews to identify forms and procedures – December thru March
(Note: other duties of the project team at 5 week intervals will interrupt for 4 days at a time)
. Compile a list of all the forms and procedures to be eliminated – April thru May
. Get approval sign offs for the eliminations – May
. Produce 2 new manuals – June thru September
. Get sign offs for the project - October
5.3 Other Schedule Related Information
. Staff can only devote 12 hours per week